Prague Congress Centre goes green

  • Published by Ozgur Tore

Prague Congress Centre

Prague Congress Centre has completed the complex reconstruction of technical equipment that will result with a cut down of the annual operating costs by 30%. The first months have already indicated that the percentage of the savings can be even higher. The reconstruction was done according to the plans in full operation by ENESA.

From September 2015 to November 2016 Congress Centre hosted nearly 200 events and 500 000 visitors proceeded its gates. No one had a clue that the biggest reconstruction of technological equipment since the 70s when the Congress Centre was built was taking place. “At the time when we were signing the contract PCC had contracted events for hundreds of millions and it was clear that there could not be any clashes. Every step, which would have impact on the operation of the centre, had to be done at the time when there were no events planned. It was quite difficult as there are very few such days, “explains Ivo Slavotínek, General Manager of ENESA.

The reconstruction included boiler room, cooling system and air conditioning system engine room. Also the system of measurement and regulation as well as lighting system went through vast modernization and extension. The reconstruction was part of energy saving project which cost 126 million CZK and which guarantees that PCC will save 213 million CZK in ten years in total. “The reconstruction was extremely vast and at the beginning we were worried but everything went well,” says Luděk Bednář, Technical Department Manager.

The project is ensured in the form of energy performance contracting (EPC), therefore PPC can annually count with 21, 3 million CZK either from the saved operational costs or from the supplier of the project who commits to defray the difference between the guaranteed and the real saving. “The results reached since April 2016 are promising. In comparison with 2016 the energy consumption in the last ten months has remarkably decreased. We already know that the guaranteed saving which is constantly going down in the first year and is now 16, 4 million CZK will be noticeably surpassed,” informs Ivo Slavotínek about the first results.

ENESA is interested in further increase of PCC energy effectiveness and is ready to use the energy management which was beneficial at several similar projects in buildings like National Theatre, Czech Philharmony, Stavovske Theatre etc.

Booking.com
Advertisement
Advertisement

Most Read in this category since 01.01.2017

  • 1
  • 2
  • 3
  • 4
  • 5
Prev Next

Destinations

Spend a Romantic Weekend in Tallinn, Estonia

Spend a Romantic Weekend in Tallinn, Estonia

Beginning of December 2016, me and my wife visited Tallinn, the capital of Estonia, and if you are searching for a romantic weekend, then you should consider Tallinn. The Estonian capital offers tra...

Best of Greek Islands with Celestyal Cruises

Best of Greek Islands with Celestyal Cruises

In Summer 2016, I had chance to sail to Greek Islands with the Celestyal Cruises. In an organization with Karavan Cruises, travelers enjoyed best of Greek islands with Celestyal and received a compl...

Unique and Luxurious Vacation Destination in Turkey: Cappadocia

Unique and Luxurious Vacation Destination in Turkey: Cappadocia

ftnNEWS would like to present you a unique vacation idea here in Turkey: Cappadocia Region. Located on the central Anatolia plateau within a volcanic landscape sculpted by erosion to form a successi...